This weekend saw the refurbished opening of the first of the Preferred Location buildings in Port Orleans Riverside's Alligator Bayou section. Building 14 appears to have replaced building 39 in the refurbishment schedule, so with the reopening of building 38 last week, refurbished rooms are now available in AB buildings 14, 36, 37 and 38 (plus the Acadian House and Magnolia Terrace mansion buildings).
There will now be a short break during the holiday period and then work will commence mid-January on converting Oak Manor to the new Royal Rooms. The projected opening date for this section is 17 February, with Parterre Place following a month later. [Update: Opening of Royal Rooms in Oak Manor has been delayed by three weeks to 9 March]