- Building 2 — Jan 6 – Feb 9, 2018
- Building 3 — Jan 23 – Feb 25, 2018
- Building 1 — Feb 10 – Mar 13, 2018
- Building 5 — Feb 26 – Mar 31, 2018
- Building 4 — Mar 14 – Apr 16, 2018
- Building 6 — Apr 1 – May 4, 2018
- Building 7 — Apr 17 – May 20, 2018

No further details or photos are available as yet, but the work will most likely include changing out the carpeting for hard wood-effect flooring, possibly adding a shutter of some sort between the bedroom and the vanity area, and other general decor and soft goods replacements including the addition of a larger Smart TV hung on the wall. I would be most surprised if we didn’t also see some of the added features that have been popping up at other resorts (for example Pop Century) such as USB charging sockets, extra storage options, etc. And if we are really lucky, perhaps something a little less stark than the plain-white bed linen that recently appeared at the resorts. Only time will tell.
Once French Quarter is complete, refurbishment will commence on Riverside’s Alligator Bayou section, and finally the Riverside Magnolia Bend mansion buildings will complete the project in 2019.