- Magnolia Bend, Acadian House: starts 26 June 2011, for approx. six weeks
- Magnolia Bend, Magnolia Terrace: starts 31 July 2011, for approx. six weeks
- Alligator Bayou, Lodges 36, 37, 38, 39: starts 25 October 2011, for approx. eight weeks
- Magnolia Bend, Oak Manor: starts 15 January 2012, for approx. five weeks [Royal Themed Rooms]
- Magnolia Bend, Parterre Place: starts 19 February 2012, for approx. five weeks [Royal Themed Rooms]
- Alligator Bayou, Lodges 24, 16, 17, 28: starts 3 April 2012, for approx. eight weeks
- Alligator Bayou, Lodges 14, 27, 18, 15: starts 8 May 2012, for approx. seven weeks
- Alligator Bayou, Lodges 25, 35, 26, 34: starts 5 June 2012, for approx. eight weeks
I have no idea why the schedule for the two mansion buildings which are due for the 'Royal' treatment (Oak Manor and Parterre Place) is slightly shorter than the other two buildings - you'd have thought they would actually take longer to complete. Time will tell I guess.