French Quarter Courtyard Refurbishment, 9 Jan - 2 March 2012

Unread post by The Sassagoula Sentinel »

The French Quarter Courtyard (behind the main lobby building) will be undergoing refurbishment work starting on Monday 9th January for approximately 8 weeks. The central area, from the lobby doors out towards the sidewalk, will be boarded up during this period but walkways will be available on either side of the courtyard.

Daily construction work should not start before 9am and the estimated completion date is 2nd March 2012. (Thanks to John Miller for the photos)

Image Image Image Image Image Image Image Image Image



Update on 19 March: Some more recent guest photos (see http://www.disboards.com/showthread.php ... st44363512) show that work is a little behind schedule, and is looking like it will be completed nearer to the end of March.

6 March:
Image

13 March, the section nearest to the main lobby is pretty much done now, and some of the walls are down:
Image



Update on 17 April: The work was completed a while before Easter, a couple of weeks behind the original schedule. Here's a photo from DISer 'pixarmom' of the finished courtyard:

Image