- Buildings 15 and 28 will be re-opening on Friday 25 May as planned.
- Next to commence work will be building 25 (instead of 18 as originally planned) which should be ready for re-opening on 8 June (or shortly after).
- Building 18 will now be started on 3 June, due for completion on 15 June.
- Building 39 will be started on 10 June and finished on 22 June.
Slight changes to the Alligator Bayou refurbishment order
Forum rules
Comments are welcome in response to news posts, but you can't start your own news topics here.
Comments are welcome in response to news posts, but you can't start your own news topics here.
-
- Posts: 416
- Joined: April 6th, 2011, 11:32 am
Slight changes to the Alligator Bayou refurbishment order
There have been a few minor adjustments to the order of the refurbishment schedule for the Port Orleans Riverside Alligator Bayou area: