The Alligator Bayou guest room refurbishment program is continuing apace, with one new building commencing work every Sunday. Building #39 closed today, and building #34 is due to close on Sunday 17th June. The work is generally taking twelve days per 64-room building, so #39 and #34 are intended to be returned for guest use on the 22nd and 29th of June respectively.

As previously mentioned, the ‘twenties’ numbered buildings are taking slightly longer to complete due to the additional roofing work that is being carried out, which is being further hindered by the wet Florida summer weather. Buildings #27 and #25 are currently estimated to be returned for use on the 20th and 27th of June, but those dates are still somewhat uncertain.

Finally, buildings #26 and #35 will both be closed together on Sunday 24th June, which will signal the final goodbye for the last few non-refurbished guest rooms at Port Orleans. By the end of the first week in July there should be just one building still undergoing renovation (#26) which will hopefully be completed around the third week in July.

For the latest updates, please keep an eye on www.portorleans.org/rehab.php.


The work on the main lobby at Port Orleans Riverside is also moving along well now, with the new chandelier already hoisted up into place. Work continues on laying the fabulous new tiling, and currently the plan is for the construction walls to be removed overnight on Wednesday 20th June, reopening for guests on 21st June.

Update on 20 June: The lobby reopening has been slightly delayed until around Monday 25 June due to extra work being done on the new floor tiles (and drying time).