Slight changes to the Alligator Bayou refurbishment order
Posted: May 23rd, 2012, 5:15 am
There have been a few minor adjustments to the order of the refurbishment schedule for the Port Orleans Riverside Alligator Bayou area:
- Buildings 15 and 28 will be re-opening on Friday 25 May as planned.
- Next to commence work will be building 25 (instead of 18 as originally planned) which should be ready for re-opening on 8 June (or shortly after).
- Building 18 will now be started on 3 June, due for completion on 15 June.
- Building 39 will be started on 10 June and finished on 22 June.